Carnegie Learning Center Kingston City School District Project Title: Date of Report: Total Pages: Carnegie Learning Center July 31, 2011 pages Subj...

1006KB Sizes 0 Downloads 12 Views

Recommend Documents

2016 Carnegie Science Awards - Carnegie Science Center
Material Science for the 2015 ASM International Convention in October. He also .... Email: [email protected] ...... Int

Restaurants Located Near Carnegie Center
Carnegie Deli , 214 Carnegie Center, Princeton, NJ 08540. (609) 452-1632. On-Site. 5. Metro Café, 506 Carnegie Center,

Carnegie-Knight Initiative - Shorenstein Center
the Chauncey Bailey Reporting Project, in which 25 students working in a ... social issues surrounding the murder of an

2008 carnegie science awards silent auction - Carnegie Science Center
May 9, 2008 - 2. 3. Evening Agenda. 6:30 - 7:45 pm. Strolling Dinner, Silent Auction and ..... by Steeler top brass, Dan

Kid's Villa Learning Center - Kids Villa Learning Center
Kid's Villa Learning Center's Menu. All A.M. Snacks and Lunch are served with 2% Milk. PM snack is served with water. ..

Creative Kids Learning Center Creative Kids Learning Center
1456 Berlin Turnpike. Berlin, CT 06037. 860-828-0101. Fax 860-828-7702. Our Mission Statement. Our Mission Statement. To

Skimming - UNC Learning Center
What Is Skimming? Skimming is a strategic, selective reading method in which you focus on main ideas or specific topics.

Capri Cosmetology Learning Center
Family Educational Rights and Privacy Act (FERPA). 33. Consumer Disclosures. 34-35. This was written and published by: C

Learning Resource Center
Double Feature: Daddy Day Care and Daddy Day Camp. 1014000044065. 111. Taxi. 1014000044040. 112. Islamic Art : Mirror of

Deep Learning at NAVER - Machine Learning Center
Apr 24, 2015 - Speech recogniCon (acousCc modeling). 3. • Powerful classifier. • Speech recogniCon. NAVER speech rec

Carnegie Learning Center Kingston City School District Project Title: Date of Report: Total Pages:

Carnegie Learning Center July 31, 2011 pages

Subject: Progress Report Number: 009 Attachment: None

Work Items complete through July 31, 31, 2011, 2011, are as follows: follows: EXTERIOR WORK ITEMS: Excavation / Exterior Work: Work: • Installation of underground conduit for the data, telephone and fire alarm systems connection to the main building is complete. • Excavation, trenching, running pipe for utility connections (water, gas, and electric) to street are all completed. Final electric power is installed and operational in building. Water is almost completed and running inside building. • Installation of new entry is nearly completed. • Canopy is installed over new main entry – finish work is required. • Installation of all stone work is complete. Installation of pre-cast architectural stone is nearly complete. • Installation of historic front entry is nearly complete except for bluestone steps. • Mechanical condensing unit has been set and connection to building is ongoing. • Installation of rooftop mechanical equipment is complete. Building Envelope: Envelope: • Re-pointing of existing stone and brick veneer is complete. Cleaning of exterior façade is complete • Additional roof repairs at the existing building are complete. INTERIOR WORK ITEMS: Existing Building – Cellar Level: Level: • Ductwork / piping installation is complete. • Electrical roughing is complete – permanent electric service complete. • Interior wall framing is complete – window openings are being framed. • New windows are installed. Wood trim is completely installed. • Hollow metal door frame installation complete. • Installation of elevator is ongoing. • Installation of ceramic tile walls in bathroom is nearly complete. • Finish painting has begun and continues. Existing Building – First Floor / Attic Level: Level: • Electrical roughing is complete.

Kingston City School District Carnegie Learning Center Progress Report No. 009

• • • • • • •

August 01, 2011

Framing is complete at first floor. Hollow metal door frame installation is in progress. Suspended ceiling tile installation is in progress. Installation of ceramic tile walls in bathroom is nearly complete. Finish painting has begun and continues. Detailed woodworking is in progress. Window restoration is complete and installation of all window wood trim is complete

UNDERGROUND CONDUIT INSTALLED FROM EXISTING HIGH SCHOOL TO NEW BUILDING.

Prepared by KSQ Architects

Page 2 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

EXISTING SIDEWALK WAS REMOVED TO ACCOMMODATE THE NEW CONDUIT ACROSS THE ROADWAY.

Prepared by KSQ Architects

Page 3 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

NEW WINDOWS

NEW CANOPY STONE INSTALLATION

NEW ELECTRIC SERVICE

Prepared by KSQ Architects

Page 4 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

ENTRY CANOPY HAS BEEN INSTALLED.

Prepared by KSQ Architects

Page 5 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

NEW MECHANICAL SYSTEMS ARE INSTALLED OUTSIDE THE BUILDING. FINAL CONNECTIONS ARE PENDING

Prepared by KSQ Architects

Page 6 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

BRICK & STONE REPOINTING AND CLEANING IS COMPLETE

ORIGINAL WINDOWS HAVE BEEN REPAIRED AND RESTORED.

RECONSTRUCTION OF HISTORIC ENTRY IS COMPLETE

Prepared by KSQ Architects

Page 7 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

BRICK & STONE REPOINTING AND CLEANING IS COMPLETE

RECONSTRUCTION OF HISTORIC ENTRY IS COMPLETE

Prepared by KSQ Architects

Page 8 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

NEW WINDOWS IN BASEMENT ARE INSTALLED

Prepared by KSQ Architects

Page 9 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

INSTALLATION OF NEW WATER MAIN CONNECTION TO STREET IS COMPLETE

Prepared by KSQ Architects

Page 10 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

STONE INSTALLATION

Prepared by KSQ Architects

Page 11 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

ORIGINAL WOOD TRIM WAS REMOVED, STRIPPED OF ORIGINAL FINISH AND REINSTALLED AND WAITING FOR FINAL FINISHES TO MATCH ORIGINAL.

Prepared by KSQ Architects

August 01, 2011

FINAL PAINTING IN PROCESS

Page 12 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

NEW WOOD TRIM, BASEBOARDS, AND WAINSCOT IS BEING INSTALLED IN MAIN FLOOR LARGE CLASSROOMS.

Prepared by KSQ Architects

Page 13 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

NEW ELEVATOR IS BEING INSTALLED.

Prepared by KSQ Architects

Page 14 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

ELEVATOR HAS BEEN DELIVERED TO THE CONSTRUCTION SITE.

Prepared by KSQ Architects

Page 15 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

LOWER LEVEL: NEW WINDOWS ARE INSTALLED. NEW WOOD WINDOW TRIMS ARE INSTALLED, AND FINAL PAINTING HAS STARTED.

Prepared by KSQ Architects

Page 16 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

NEW WOOD TRIM, BASEBOARDS, AND WAINSCOT IS BEING INSTALLED IN MAIN FLOOR LARGE CLASSROOMS.

Prepared by KSQ Architects

Page 17 of 18

Kingston City School District Carnegie Learning Center Progress Report No. 009

August 01, 2011

CERAMIC WALL TILE IN NEW BATHROOMS IS NEARLY COMPLETE.

Prepared by KSQ Architects

Page 18 of 18